Kish Gas Field Development Electrical Power Plant Project Kish Power Plant and Steam Generation project has been planned with the aim of supplying energy consumption of Kish Gas Refinery. The contract includes six units of gas turbine generator type Hitachi H25, three 80 t/h HRSG boilers and three 190 t/h Industrial Boilers and accessories on EPC basis. UED as a leader of the consortium of Ghods Niroo Engineering, NTN Co and Jahan Pars participated in this tender and finally the group succeeded in presenting the best technical and financial proposal. The contract has been awarded to UED Consortium.


  •  Project:  Kish Power Plant and Steam Generation project
  •  Contract Type: EPC
  •  Location: Gorzeh - Hormozgan Province
  •  Client: Petroleum Engineering & Development Co. (PEDC)
  •  Capacity:  180 MW
  •  Units Configuration:  6 x 30 MW GTG + 3 x 80 t/h HRSG + 3 x 190 t/h Boilers
  •  Status:  Finished